May 2016 Maabjergvrket, Holstebro: Replacement of 1 transformer differential- and 3 overcurrent protection relays.
April 2016 Advokatfirma Dahl/Topdanmark Insurance: Technical assistance concerning 60 kV grid operation.
February 2016 Fortum Vrme, Vrtan Verket, Stockholm, Sweden: Current- and voltage transformer primary injection test to generator protection. Current transformer test reports. Test of synchronizing voltages before first synchronizing.
February 2016 Limfjordens Bioenergi: 10 kV Voltage transformer fault finding.
January 2016 Maabjergvrket, Holstebro: Fault finding in transformer differential protection relay.
November 2015 - jan 2016 Energinet.dk: Offshore Substation for windfarm Horns Rev 3. Electrical supervisor at HSM yard Rotterdam, Netherlands.
September 2015 NordEnergi: Test of 30 60 kV distance relays.
August 2015 Hjoerring district heating plant: New generator protection. 58 MW
June 2015 Aars district heating plant: New generator voltage regulator. 3,5 MW
November 2014- June 2015 DONG ENERGY Offshore Substation for windfarm Goodewind 1+2: Site Integration Test of High Voltage (HV) and Medium Voltage (MV) systems consisting of 2 150 kV GIS switchgear bays, 2 180 MW transformers and 20 34 kV switchgear bays on both platforms. Build at Fabricom, Antwerp, Belgium.
November 2014 Reno Nord district heating plant: Fault finding in generator protection, and installation, test and commissioning of new temporary generator protection. 8 MW
September-Oktober 2014 Energinet.dk, TSO in Denmark. Test of 18 150 kV distance relays.
September 2014 Aars district heating plant: 5 kV insulation resistance test of generator. 7 MW
September 2014 Aars district heating plant: Replacement of new synchronizer. Engineering, test and commissioning
September 2014 Thy-Mors Energi: Fault finding and test of 2 60 kV distance relays.
August 2014 TopDanmark Insurance company: Report concerning operation of 60 kV grid system.
June-July 2014 DONG ENERGY Onshore Substation for Westermost Rough, Hull England. Assistance for finishing Site integration test.
January-May 2014 DONG ENERGY Offshore Substation for windfarm Westermost Rough: Site Integration Test of High Voltage (HV) and Medium Voltage (MV) systems consisting of 2 150 kV GIS switchgear bays, 2 160 MW transformers and 14 34 kV switchgear bays. Build at STX, Saint Nazaire, France.
December 2013 Kyndby turbine 2 Power Plant: Test of generator protection. 250 MW
Oktober-December 2013 Koege district heating plant turbine 8. Installation and commissioning of new generator protection.
Oktober 2013 Avedore Power Plant: Fault finding on gasturbine 522 generator protection. xx MW
September 2013 Dong Energy Borkum Riffgrund I: Metering report to grid operator TenneT (TSO in NL and part of Germany)
September 2013 Aars district heating plant. Replacement of syncrocheck relay and test of generator protection. 7 MW
September 2013 Hirtshals district heating plant: 5 kV insulation resistance test of generator, test of generator protection and replacement and test of new 10 kV overcurrent relay. 18 MW.
May 2013 Offshore Substation Walney: Report concerning primary test of relays.
April 2013 Aars district heating plant. 5 kV generator insulation resistance test. 7 MW
Marts-July 2013 Offshore Substation for windfarm Borkum Riffgrund I: Site Integration Test of High Voltage (HV) and Medium Voltage (MV) systems consisting of 2 150 kV GIS switchgear bays, 2 140 MW transformers and 20 34 kV switchgear bays. Build at Bladt Industries, Aalborg, Denmark.
January 2013 Investigation of Bangui Bay wind farm for faulty full load operation. Evaluation of the presence of necessary in build wind turbine capacitor installation . 34 MW
December 2012 Hjorring district heating plant. 5 kV insulation resistance test of generator. 60 MW
September 2012 Koege district heating plant turbine 7: 5 kV insulation resistance test of generator, test of generator protection and replacement and test of new synchronizing check relay.
September 2012 Frederikshavn district heating plant: Test of generator protection. 18 MW
September 2012 Maabjergvaerket District heating plant: Replacement and test of new df/dt relay. 28 MW
June 2012 Asnaes Power Plant: Programming of new settings in existing generator protection, and test of the new settings. 280 MW
May 2012 Maabjergvaerket District heating plant: Fault finding in df/dt protection. 28 MW
April 2012 Kyndby turbine 1+2 Power Plant: Programming of new settings in existing generator protection, and test of the new settings. 2x250 MW
April 2012 Thisted district heating plant. Test of generator protection. 4 MW
February 2012 Reno Nord district heating plant. Test of generator protection. 8 MW
February 2012 Investigation of Bangui Bay wind farm for faulty full load operation. Installation of distance relays for fault diagnosis. 34 MW
October 2011 Hanstholm district heating plant. Fault finding in 1 generator protection and overall test of generator protection for 4 gas engines. 4x 1,6 MW